Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2007 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. | |
| 06/26/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor started installing landscaping around site. | |
| 06/13/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor forming up inlet and sidewalk scupper, also placing ex. curb around parking area. | |
| 06/07/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor paved parking area. Spoke to site super in regards to final inspection. Contractor needs to stabilize all area disturded by construction. | |
| 05/15/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to reinstall wattle on west side of project. Spoke to site super in regards to. | |
| 04/17/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. Contractor cut basin on north side. | |
| 03/20/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Spoke to super in regards to: 1 - Cleaning out wash out pit. 2 - East slope bank needing rip rap protection. (steeper then 2 to 1) 3 - Contractor will install curb and sidewalk for ped. path on east side of building. |
|
| 02/05/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | 1- Pull dirt off east fence. 2- Keep wattle uncovered west and north side of project. |