Inspection History Details
Permit: T06BU01632
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2007 | ENGINEERING PRE-CONSTRUCTION | Approved | CONTACTS: CHRISTEN (PATHWAY DEV) 271-1566 CHIP (JANC CONSTRUCTION) DISCUSSED APPROVED STORM WATER PLAN IMPLEMENTATION. 18 LOTS, SILT FENCE AROUND THREE SIDE OF PROJECT. SUPERINTENDENT WILL CALL FOR RE-INSPECTION WHEN SEDIMENT CONTROLS ARE INSTALLED. |
|
| 07/25/2007 | ENGINEERING PRE-CONSTRUCTION | Not ready for Inspection | NO CONSTRUCTION ACTIVITY ON SITE, CONCTRUTION TRAILER ON SITE, LEFT NOTICE FOR PRE-CON REQUIREMENT | |
| 06/01/2007 | ENGINEERING PRE-CONSTRUCTION | Not ready for Inspection | NO ACTIVITY ON SITE |