Permit: T06BU01541

Parcel: 11201078C

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
06/28/2012 GRADING - INTERMEDIATE Approved
10/05/2011 GRADING - INTERMEDIATE Continued INSPECTION CALLED IN TO KEEP PERMIT FROM EXPIRING, NO STORM WATER CONCERNS AT THIS TIME.
07/08/2011 GRADING - INTERMEDIATE Approved
02/16/2011 GRADING - INTERMEDIATE Continued GRADING PERMIT HAS BEEN RENEWED. SITE HAS NEW OWNER AND CONTRACTOR CONSTRUCTING TWO NEW HOMES.
SITE IS STILL UNDER A STORM WATER PEMIT, HOWEVER THE PERIMETER OF THE SITE HAS BEEN HARDSCAPED. ALL CURBING, ACCESS ROADWAY , RET/DET BASINS AND PERIMETER FENCING HAS BEEN CONSTRUCTED. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/10/2009 GRADING - INTERMEDIATE Continued NO CHANGES SINCE LAST INSPECTION. NO SIGNIFICANT ACTIVITY ON SITE.
09/05/2008 GRADING - INTERMEDIATE Partial Approval MET WITH OWNER, SITE PERIMETER IS STABILIZED.
HOWEVER, UNDEVELOPED LOTS NEED SEDIMENT CONTROLS TO PREVENT RUN-OFF FROM SILTING IN THE RET/DET BASINS.
SITE ACCEPTS STORM WATER FROM THE DEVELOPMENT TO THE SOUTH - POTENTIAL FOR DRAINAGE PROBLEMS DUE TO RUN-ON EROSION.
WEST BASIN HOLDS WATER >24 HRS.
05/12/2008 GRADING - INTERMEDIATE Correction Required MET WITH DEVELOPER AND BUILDER, THEY PROVIDED A SOILS REPORT, STAMPED PLAN, AND PROPOSED FIX FOR RETENTION/DETENTION BASIN 'B'. BASIN DOES NOT DRAIN.
DEV/OWNER STATED THAT THE BASIN REPAIR, AND ALL SITE WORK TO INCLUDE COMMON AREAS WILL BE COMPLETED AS SOON AS FEASIBLE.

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
04/21/2008 GRADING - INTERMEDIATE Partial Approval MET WITH DEVELOPER, REALTOR, AND CLIENT ON EROISION PROTECTION REQUIREMENTS FOR THE SLOPE LOCATED ALONG THE SOUTH PERIMETER OF THE SITE. SLOPE IS BEING USED AS A 10' EASEMENT SET BACK AND VEGATATION HAS NOT BEEN REMOVEDFROM IT. SLOPE IS APPROXIMATELY 3:1. NO ADDITIONAL STABILIZATION MEASURES ARE REQUIRED ON THE GRADING PLAN. HOWEVER, IF THE DEVELOPER ENCROCHES INTO THE 10' BUFFER AREA, SUPPLEMENTAL STABILIZATION WILL BE REQUIRED.
02/25/2008 GRADING - INTERMEDIATE Correction Required FOLLOW UP ON COMPLAINT, RET/DET BASIN "B" DOES NOT DRAIN (PERC) PROPERLY PER DESIGN STD (<24 HRS). BASIN IS ALSO ACCEPTING STORM WATER FROM COUNTRY CLUB BLVD, NOT SHOWN ON APPROVED PLAN. CONTRACTOR PUMPING STORM WATER INTO RIGHT-OF-WAY.

RECOMMEND:
1) COMPLETE CONSTRUCTION OF BASIN "B" PER THE APPROVED GRADING PLAN, MEET ALL DIMENSIONS AND ELEVATIONS SHOWN (4:1 SIDE SLOPES W/2' ELEVATION FROM BOTTOM OF BASIN TO TOP OF WEIR).
2) INSTALL A BIRM OR VALLEY GUTTER AT ENTRANCE OF SITE TO ALLOW STORM WATER TO CONTINUE TO DRAIN ALONG RIGHT-OF-WAY AND NOT INTO BASIN.
3) REMOVE SILT LAYER FROM BOTTOM OF BASIN AND SCARIFY.
4) WHEN PUMPING WATER OUT OF BASIN, USE A FABRIC SOCK OR STRAINER ATTACHED TO THE OUTLET PIPE, TO DROP SILT OUT PRIOR TO LEAVING SITE
01/22/2008 GRADING - INTERMEDIATE Correction Required 1) STABILIZE SIDE SLOPES FOR BASIN "B" - SOIL IS DISCHARGING OFF SITE.
2) RET/DET "B" HOLDS WATER GREATER THAN 24 HOURS. BASIN IS DESIGNED TO PERC.
09/21/2007 GRADING - INTERMEDIATE Correction Required THERE ARE TWO RET/DET BASINS BEING CONSTRUCTED ON SITE. ENSURE YOU PROVIDE A BASIN CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THEY WERE CONSTRUCTED IN ACCORDANCE WITH THE APPROVED PLANS.