Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T06BU01328

Parcel: 132130570


Addresses:

1051 E BENSON HY

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
10/16/2007 GRADING - FINAL Approved Contractor completed punch list. Contractor provided letter from engineer.
10/04/2007 GRADING - FINAL Not ready for Inspection Contractor placed concrete for new basin inlets.
09/27/2007 GRADING - FINAL Correction Required Went over punch list. Contractor still needs to complete items 1, 2, 7, 9, 10 and 11.
09/13/2007 GRADING - FINAL Correction Required Met with owner and engineer on site and went over punch list. Also, what will be needed to be complete for temp C of O.
09/11/2007 GRADING - FINAL Correction Required Spoke to Josh Richardson in regards to punch list. Josh wants to set a 3rd meeting on site to go over punch list.
09/06/2007 GRADING - FINAL Not ready for Inspection Met on site with owner, engineer and contractor. Went over punch list. Contractor needs to address items before TCO can be issued.
08/22/2007 GRADING - FINAL Partial Approval Met Rich on site went over:
1- parking area.
2- HC parking.
3- Bike parking.
4- What will be needed for a temp C of O.
08/17/2007 GRADING - FINAL Partial Approval Met with Rick and Charlie on site went over prelim punch list.
08/09/2007 GRADING - FINAL Partial Approval Spoke to Engineer for site in regards to cert. letter for basins and drainage. Explained it needs to be sealed with his stamp.
08/07/2007 GRADING - FINAL Denied This is a prelim punch list. IT IS NOT A COMPLETE PUNCH LIST, contractor will needs to call in re-inspection:
1- Provide letter from engineer in regards to D.S. chapter XIV, section 14.2(7). Regards to drainage and detention/retention basins.
2- Separate all construction activity and bedris from public access.
3- Complete all striping, per approved plans.
4- Install bike parking.
5- Stabilize all areas disturbed by construction outside of grading limits.
6- Install rip rap pad north corner of project, per note 5 on the approved plans. (extend backside of wall and use filter fabric.)
7- Install outlet wier and wall openings, per approved drawings, detail 18 on sheet 5 of 5. Basin #1.
8- Install inspection ports to basin #1, per approved drawings, note 32 on sheet 3 of 5 and detail 23 on sheet 5 of 5.
9- Install all inlets to basin #1, per approved drawings, detail 21 and 22 sheet 5 of 5.
10- Have all changes to approved drawings, approved. submit revised drawings at 201 N. Stone.
11- Complete all concrete work or install safety barrier.
12- Install gates on trash enclosure, per approved drawings.
13- Clean trash out of gutter drain behind building 8.
14- Address note 26 and 27 on northeast corner per approved plans.
15- Install HC parking with trucated domes, per approved drawing.
16-Install all wheel stops, per approved drawing.
17- Install sidewalk, per note 12 on approved drawing.
18- Install outlet wier per approved drawing, rip rap opening, basin #2
19- Install rip rap, per approved drawings detail 15B. (end of gutter)
20- Provide info on note 4, cutoff wall. Sheet 2of 5.
21- Install water harvesting area, per note 34 on sheet 2 of 5.
22- Address erosion around basin #2.
Super on site given copy of inspection. Went over all items with super.
07/19/2007 GRADING - FINAL Cancelled IVRS - AP canceled
07/19/2007 GRADING - FINAL Correction Required Contractor needs to call in final inspection. Need to address drainage channel along Benson Highway, channel has erosion and slope bank for channel is 2 to 1 and less. Contrator needs to stabilize all areas disturbed by construction.
03/20/2007 GRADING - FINAL Partial Approval Contractor installing north basin per approved plans. Contractor will need to provide conpaction test reports for basin bottom.
03/15/2007 GRADING - FINAL Partial Approval Met with Charlie, contractor complete excavtion for basin. Per approved drawings.
01/12/2007 GRADING - FINAL Not Applicable Met with concrete foreman on site. contractor to start grading streets on site 1/12/07. Contractor needs to keep 2 to 3% on all public access areas.
11/29/2006 GRADING - FINAL Correction Required Contractor graded lot with no stormwater controls installed. Spoke to super, told him all grading must stop until controls are installed.