Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T06BU01328
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/21/2007 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. | |
08/01/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Issued correction notice. Contractor needs to address: 1- Address spillway on the southwest basin. 2- Address erosion in drainage channel southwest side of project. Spoke to site super in regards to. If not addressed I will issue a notice of violation. |
|
05/16/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to keep wash out cleaned up. | |
05/09/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to install controls for north basin inlets. Spoke to site super in regards to. | |
02/12/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to: 1- Remove broken hay bales from drainage channel. Next to Benson Highway. 2- Clean up wash out north side of property, next to fence. 3- Repair wash bank north side of project. Spoke to site super. |
|
12/18/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to: 1- Compact berm a long Benson. 2- Replace damaged straw bales. Northside. 3- Install silt fence a long wash. Northside of project. 4- Repair wash bank damaged by construction. 5- Remove spoil material a long property line with Motel 6. |