| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2006 | ENGINEERING PRE-CONSTRUCTION | Approved | STORM WATER PRE-CON MEETING PERFORMED (JIM KINSER 444-4904) : 1) INSTALL SILT FENCE OR EQUIVALENT AS AGREED TO PRIOR TO CONSTRUCTION. SEDIMENT CONTROLS ARE NOT REQUIRED IN AREAS WITH CURBING OR THAT HAVE BEEN STABILIZED. 2) INSTALL STABILIZED CONSTRUCTION ENTRANCES PER PLAN. 3) SWEEP UP TRACKED MATERIAL OFF OF ROADWAYS AS NEEDED. 4) MAKE CHANGES TO SWPPP DRAWING PER 10/31/01 INSPECTION. 5) POST A SIGNED COPY OY YOUR NOI AT THE ENTRANCE. 6) PROVIDE A DESIGNATED CONCRETE WASH OUT WHEN REQUIRED. |