Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/02/2007 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. | |
| 10/12/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Spoke to Pat site super. Contractor grading for paving. Contractor is sweeping as needed. | |
| 06/14/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Site unchanged from last inspection. Spoke to Miss Gomez, home owner 2025 Rofur Cir. Contractor has not made contact with her yet in regards to work being done behind her house. I told Miss Gomez if the contractor did not make contact in the next few weeks I would set up a meeting with them and her. | |
| 06/13/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor cleaning alley. Spoke to Patrick in regards to installing controls in catch basin on northwest corner of project. | |
| 06/11/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Met on site with Patrick site super, contractor cleaned street. Contractor still needs to clean alley way. Patrick asked me to return on 6-13-07. | |
| 06/08/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Issued Correction Notice, contractor needs to: 1- Clean track out. 2- Install construction entrance. 3- Install controls in wall opens. 4- Clean alley west side of project. Spoke to Patrick site super at 1303 hours, via cell phone. Left paper work on front door to trailer. |
|
| 05/15/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to: 1- Stop all vehicle parking in basin. 2- Keep wash out cleaded up. |
|
| 04/20/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor will need to call for inspection of stormwater pipe and provide compaction test. Spoke to site super in regards to. |