Permit: T06BU00279

Parcel: 140420150


Addresses:

2660 E MEDINA RD

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
12/26/2007 STORMWATER FOLLOW-UP INSP Approved
09/11/2007 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to Chris site super, in regards to:
1- Drainage channel side slopes on east side of project.
2- Hand rail along channel.
3- Provide asbuilt elevation for east side curb work.
4- Contractor using drawings that is not approved for construction. I told Chris they should be using the approved drawings. I explained when the final inspection is called in I will use the approved drawings. Chris said he had checked the drawings and they are the same.
5- Sweep streets.
Contractor given copy of Re-fee policy.
08/24/2007 STORMWATER FOLLOW-UP INSP Correction Required Site still not ready for inspection. I asked Chris Site super how much time does he he to get the site in complaince. Chris said he needed untill Tuesday 8/28/07. I told Chris he had until Tuesday 1500 hours. If the site is not in complaince I will issue a stop work order. This is the 3rd. inspection in 5 days and site still is not in complaince.
08/23/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor given an additional 24 hours to address correction notice. Site not ready for inspection. Spoke to Chris Bush site super in regards to issue.
08/21/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice. Contractor given 2 days to:
1- Clean street west side of building.
2- Clean silt from curb cuts.
3- Address curb cut south side of project. (underminded)
4- Address wash out southeast side. (in basin/drainage channel)
If contractor does not address items will issue Notice of Violation. Spoke to Chris Bush site super in regards to issues.
08/01/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean up site track out. All the way to Tucson BLVD.
07/27/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address items 3 and 4 from inspection dated 7/25/07. Walked site with super went over remaining items.
07/25/2007 STORMWATER FOLLOW-UP INSP Correction Required Received complaint call from Clarion Hotel 6801 S. Tucson Blvd. Durning the rain from 7/24/07 mud ran off the Marriott Inn site into the parking lot of the Clarion. After my inspection of the Marriott Inn today I issued a Correction Notice giving the contractor 2 days to make repairs to:
1- Contractor needs to replace/repair stormwater controls around perimeter of project.
2- Install controls in scuppers and curb cuts. (erosion behind curb cuts and mud washing out into paved areas)
3- Clean mud from parking lot of Clarion Hotel 6801 S. Tucson Blvd.
4- Clean all wash out from detentiion basin. Ensure sub-contractor use wash out area.
5- Contractor needs to complete SWPPP inspection per AZ permit. (no inspection since 2/07)
6- Repair construction entrance.
If contractor does not address items I will issue a stop work order. Spoke to site super in regards to issues.
07/19/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice, contractor needs to:
1- Repair/replace wattle around site. (around perimeter)
2- Clean wash out from basin.
3- Remove sand and stop all activity in basin.
4- Repair construction entrance.
5- Stabilize all areas disturbed by construction outside of grading limits.
6- Stop all activity outside of grading limits.
Contractor has 4 days to address issues. If issues are not addressed I will issue a notice of violation. Spoke to site super in regards to.
06/07/2007 STORMWATER FOLLOW-UP INSP Correction Required Spoke to Chris site super in regards to southwest side, slope may need rip rap. Contractor also needs to stop storing material in basin. Contractor to survey side slope and contact me in regards to.
06/07/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor finished paving and striping. Only one HC ramp updated.
05/11/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Remove dirt from curb line and install controls around spoil.
2- Re-install construction entrance.
3- Keep waqsh out cleaned up. Ensure wash out area is used by subs. 2nd. notice.
Spoke to site super in regards to.
04/19/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor need to ensure all wash out is washed out in an approved wash out area. All mason, painter, drywall and concrete.
03/19/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to make repairs to stormwater controls on west side of project.
02/22/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- Keep streets clean of track out.
2- Re-cut channel on west side.
3- Keep silt fence in working condition.
Spoke to site super in regards to.
02/02/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to keep wash out cleaned up.