Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2005 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 15 PSI TEST FROM METER UNDERGROUND UP AT BUILDING OVERHEAD TO ROOF TOP UNIT + WATER HEATER ONLY |
|
| 12/09/2005 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 15 PSI TEST FROM MOTOR UNDERGROUND UP AT BUILDING OVERHEAD TO ROOFTOP UNIT & WATER HEATER ONLY - OK 1. PROVIDE PERMIT FOR WATER HEATER 2. PROVIDE PETITION OF APPEAL FOR ALTERNATE FORM OF TERMPERATURE & PRESSURE RELIEF ON SITE SIGNED BY CITY WITH CORRECT INSTALLATION. 3. PROVIDE BONDING OF BUILDING GAS PIPING 4. PROVIDE 1" MINIMUM CLEARANCE FROM COMBUSTABLES FOR WATER HEATER VENT PENETRATION THRU ROOF. 5. PROVIDE 3-GALV SCREWS AT EACH JOINT OF WATER HEATER VENT AND HAVE VENT PIPING MADE UP CORRECTLY WITH APPROVED DOUBLE WALL VENT CAP. 6. PROVIDE UPPER COMBUSTION AIR FOR WATER HEATER. 7. PLUG PAN DRAIN & INSTALL NIPPLE WITH NO THREADS ON END OF 125# PRESSURE RELIEF T&P DRAIN TO HAVE 1" CLEARANCE FROM PAN. 8. SECURE ALL PIPING CORRECTLY FOR GAS. |