| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 10/03/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* TEST TO HOLD WITH NO PRESSURE LOSS. |
|
| 10/02/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE MINIMUM 10 PSI TEST AT TIME OF INSPECTION. |
|
| 09/21/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. TEST SYSTEM IN ENTIRETY. 2. T&P TO TERMINATE DRAIN. 3. PROVIDE BONDING OF BUILDING GAS PIPING. 4. SEAL PIPE PENETRATIONS. |
|
| 11/23/2005 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999*PIPING TO FURNACE TO BE ARRANGED TO PROVIDE PUL SPACE FOR WATER HEATER AND BE SECURED PROPERLY PROVIDE RIDGID PIPING FOR WATERE HEATER T & P DRAIN GRAVITY DRAIN TO DAYLIGHT TERMINATING 6" -24" FROM FINISH GRADE AT 90 DEGREE DOWN. SEAL GAS PIPING ENTRY. |