Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2005 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 15 PSI TEST FROM METER LOCATION TO EXISTING BUILDING ENTRY FOR ROOFTOP UNIT - THIS LOCATION TO BE TIED IN BY PLUMBER & SOAP TESTED METER IS ON AND FURNACE WAS RUNNING. PIPING CONTINUES TO EXISTING SERVICE ENTRANCE TO WATER HEATER ONLY. NO GAS CARD REQ'D |
|
| 12/09/2005 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* GAS METER IS ON 1. GAS PIPING & WATER PIPING TO BE MINIMUM 12" OF COVER 2. PROVIDE PIPE PRIMER THEN 10 MIL TAPE TO ALL UNDERGROUND FITTINGS & TOOL MARKS 3. EXPOSE ALL PIPE FITTINGS FOR INSPECTION THAT ARE BURIED. 4. PROVIDE BONDING OF BUILDING GAS PIPING. 5. VENT FROM WATER HEATER TO TRAVEL 1/4" PER FOOT UPHILL AND HAVE 3-GALV SCREWS AT EACH JOINT OF VENT PIPING IN WATER HEATER CLOSET. 6. PROVIDE AGA OR CSA APPROVED GAS VALVES AT ALL APPLIANCES. 7. REMOVE KINK IN VERTICAL DRAIN FOR WATER HEATER T&P 7A. HAVE ALL GAS SYSTEM UNDER TEST OR ENERGIZED WITH EXISTING GAS MOTOR - PLEASE HAVE YOUR PLUMBER CONTACT ME AT 240-0248 8. HAVE ON SITE CORRECT FITTINGS FOR TIE IN TO EXISTING GAS SYSTEM AND CAP OFF ALL UNUSED PIPING PERMANENTLY 9. IF YOU ARE ADDING ANY GAS APPLIANCES TO YOUR SYSTEM PROVIDE CITY APPROVED GAS ISOMETRIC PLAN ON SITE. |
|
| 12/08/2005 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* |