Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T05PL01839
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2006 | SITE - SEWER | Approved | IVRS - Inspection :* | |
08/23/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* - FROM MANHOLE #4 8" SDR 35 TO BUILDING AIR TEST OK NO LOSS 1. SHALL SEE CONNECTION TO BUILDING. 2. SHALL WITNESS MANHOLE VACUUM TESTING. 3. SHALL RECEIVE AUTHORIZATION TO DISCHARGE FROM PCDEQ. - FROM MANHOLE #3 8" SDR 35 TO MANHOLE #4 AIR TEST OK NO LOSS - FROM MANHOLE #2 8" SDR 35 TO MANHOLE #3 AIR TEST OK NO LOSS - FROM MANHOLE #1 8" SDR 35 TO MANHOLE #2 AIR TEST OK NO LOSS - FROM MANHOLE #1 8" DUCTILE TO EXISTING PUBLIC MANHOLE AIR TEST OK -- NO LOSS. |
|
08/15/2006 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED HOLD OVER TO 10:00 AM 8/15/06 PER TROY AT DIVERSIFIED REQUEST |
|
08/14/2006 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
08/04/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" STUB FROM MANHOLE #2 ONLY TOWARD #5 8" STUB FROM MANHOLE #3 TOWARD BUILDING 2 ONLY, 8" FROM MANHOLE #4 TO 5' FROM BUILDING 1 BEDDING, LAYING OK 1. PROVIDE CORRECT TRACER WITH SHAPING FOR BACKFILL. |
|
08/02/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #1 8" SDR TO MANHOLE #2 MANHOLE #2 TO #3 MANHOLE #3 TO #4 INCLUDING DUCTILE IRON AS SHOWN ON PLAN BEDDING, LAYING, TRACER, SHADING OK |
|
07/31/2006 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
07/26/2006 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
07/24/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* EXCAVATION ONLY FROM 5/1/06 INSPECTION NO CHANGE ON PIPING. REMOVE DEBRIS FROM PIPING AREA & PROVIDE GOOD SHADING MATERIAL. |
|
05/01/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" DUCTILE IRON FOR EXISTING MANHOLE 2820-04 TO NEW MANHOLE #1 AND 8" SDR APP. 10' TOWARD MANHOLE #2 BEDDING, LAYING, SHADING, TRACER OK 1. WILL NEED AIR TEST ON PIPING, VACUUM TEST ON MANHOLES, VERIFICATION OF GRADE, ADEQ AUTHORIZATION TO DISCHARGE AT LATER DATE. |
|
04/27/2006 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* HAD PRE-CON WITH JOE ARIZONA EXCAVATING |