Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 04/27/2005 |
PLUMBING - FINAL |
|
Approved |
IVRS - Inspection :* 1) GAS PRESSURE TEST IS OK. 2) ALL CORRECTIONS HAVE BEEN MADE. |
| 04/20/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :* 1) WHERE UNIONS ARE NECESSARY LEFT-RIGHT NIPPLES & COUPLINS SHALL BE USED. 2) INSTALL WATER HEATE IN DETACHED BUILDING. 3) VENT FROM WATER HEATER & FURNACE WHEN WITHIN 10' OF COOOLER INTAKE TO BE 3" ABOVE TOP OF COOLER INTAKE. 4) PROVIDE ROOF FLASHINGS FOR ALL PIPE PENETRATIONS THRU ROOF. 5) PROVIDE RIDGID PIPE PENETRATION THRU APPLIANCE HOUSING FOR GAS SUPPLY TO FURNACE. 6) HAVE NEW WATER HEATER ADDED TO PERMIT. 7) PROVIDE CORRECT VENTING FOR FURANCE. 8) WATER HEATER TEMPERATURE & PRESSURE RELIEF PIPING TO BE RIDGID FULL SIZE, GRAVITY DRAIN TO DAYLIGHT OR PROVIDE CITY SIGNED PETITION OF APPEAL FOR ALTERNATE FORM OF T & P RELIEF ON SITE WITH CORRECT INSTALLATION. 9) SECURE PIPE DROPS AT FURNACE & WATER HEATER CLOSET. |