Inspection Status: Partial Approval
Inspection History: ELECTRIC - CONSTRUCTION POWER
| Date |
Description |
Inspector |
Results |
Comments |
| 06/13/2005 |
ELECTRIC - CONSTRUCTION POWER |
|
Partial Approval |
IVRS - Inspection :* 1. THIS PROJECT IS A RE-DO. THE FIRST INSTALLATION WAS REJECTED BY TEP. 2. THE TEMPORARY POWER POLE AND SERVICE EQUIPEMENT HAVE BEEN RELOCATED AND REARRANGED TO MEET TEP REQUIREMENTS. 3. A NEW CLEARANCE IS REQUIRED. PLEASE SEND NOW CLEARANCE TO TEP . THIS ONE IF FOR TEMP POWER POLE/ CONSTRUCTION POWER. |
| 06/09/2005 |
ELECTRIC - CONSTRUCTION POWER |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 05/04/2005 |
ELECTRIC - CONSTRUCTION POWER |
|
Partial Approval |
|