Inspection History Details
Inspection Status: Partial Approval
Inspection History: ELECTRIC - CONSTRUCTION POWER
Permit Number - T05EL00757
Inspection Description - ELECTRIC - CONSTRUCTION POWER
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/13/2005 | ELECTRIC - CONSTRUCTION POWER | Partial Approval | IVRS - Inspection :* 1. THIS PROJECT IS A RE-DO. THE FIRST INSTALLATION WAS REJECTED BY TEP. 2. THE TEMPORARY POWER POLE AND SERVICE EQUIPEMENT HAVE BEEN RELOCATED AND REARRANGED TO MEET TEP REQUIREMENTS. 3. A NEW CLEARANCE IS REQUIRED. PLEASE SEND NOW CLEARANCE TO TEP . THIS ONE IF FOR TEMP POWER POLE/ CONSTRUCTION POWER. | |
06/09/2005 | ELECTRIC - CONSTRUCTION POWER | Not ready for Inspection | IVRS - Inspection :* | |
05/04/2005 | ELECTRIC - CONSTRUCTION POWER | Partial Approval |