Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2008 | ENGINEERING - FINAL | Approved | Contractor provided approved revised drawing for frontage access. | |
| 04/03/2008 | ENGINEERING - FINAL | Partial Approval | Met with LeeRay on site to look at accessible route from right-of-way. LeeRay to get with T.D.O.T. about furture changes to right-of-way. | |
| 03/28/2008 | ENGINEERING - FINAL | Partial Approval | Ok for temp. Contractor needs to address frontage accessibility. Per D.S. 2-08.4.1.A. | |
| 03/11/2008 | ENGINEERING - FINAL | Partial Approval | Contractor needs to: 1- Remove port-a-potty. 2- Install pilot holes for trash enclosure. Also install one cane per door (2). 3- Move wheel stops 2.5' from edge of sidewalk. 4- Remove all SWPPP controls. 5- Complete all landscape work. 6- Complete ped. access to right-of-way. Spoke to site super in regards to. |