Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/09/2010 | ENGINEERING - FINAL | Approved | WORK COMPLETED AND APPROVED ON TI PERMIT. OK TO CLOSE | |
| 01/09/2009 | ENGINEERING - FINAL | Correction Required | No activity on site. Contractor has not addressed HC accessible in rear of building. Contractor needs to address ponding in parking lot northwest corner. | |
| 06/19/2008 | ENGINEERING - FINAL | Correction Required | Issued Correction Notice. Contractor has 30 days to address: 1- Sidewalk on west side of building must be 6.5 feet wide. If item is not addressed will issued a Notice of Violation or Stop Work Order. Spoke to Ryan site super in regards to. |
|
| 06/13/2008 | ENGINEERING - FINAL | Denied | Complete all work. Address punch list dated 6/2/08. Contractor needs to address sidewalk west side of building (sidewalk needs to be 6.5'). Spoke to site super Ryan in regards to all issues. | |
| 06/02/2008 | ENGINEERING - FINAL | Denied | This is not a complete punch list. Contractor needs to: 1- Complete all work westside of building. 2- Complete all HC parking. 3- Complete all paving. 4- Stabilize all areas disturbed by construction. 5- Remove stockpiled material from site. 6- Fill all open holes in parking area. 7- Provide drainage per approved plan. 8- All items not to be completed need to be deleted from approved drawings at 201 North Stone. |
|
| 03/27/2008 | ENGINEERING - FINAL | Correction Required | Mety onsite with Ryan went over drawings and north side of project. Contractor does not want to pave north side of project. I told Ryan if they do not want to pave it someone will need to go to 201 N. Stone and have Zoning and Engineering approve. | |
| 03/04/2008 | ENGINEERING - FINAL | Denied | Conttractor needs to complete all work. | |
| 02/20/2008 | ENGINEERING - FINAL | Correction Required | Contractor needs to: 1- Clean asphalt, track out. (also west parking area) 2- Clean all wash out around site. 3- Stabilize all areas disturbed by construction before final C of O. 4- Install gates on trash enclosure. 5- Clean existing drainage channel north side of project. 6- Complete all grading to smooth uniform finish. 7- Install stabilized discharge into existing channel. 8- Remove stock pile from parking area. Spoke to Ryan site super in regards to. This is not a complete punch list. |
|
| 10/17/2007 | ENGINEERING - FINAL | Correction Required | Met with super on site. Explained that contractor needs to keep up with BMP's for site. I explained I would be back in 14 days to see if site is cleaned. If not cleaned I will issue a correction notice. | |
| 10/04/2007 | ENGINEERING - FINAL | Correction Required | Contractor needs to: 1- Clean up all wash out. 2- Sweep asphalt. Contractor is not using best BMP. |