Permit: T05CM06045

Parcel: 10705146A

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
12/04/2007 ENGINEERING - FINAL Approved
11/21/2007 ENGINEERING - FINAL Denied SEE COMMENTS FROM FINAL GRADING ISPECTION FOR PERMIT # T06BU01543 FOR DATE 11/20/07
10/24/2007 ENGINEERING - FINAL Correction Required ITEMS LISTED ON THE COMPLIANCE LETTER FOR THE TEMPORARY C OF O HAVE NOT BEEN COMPLETED. THE COMPLIANCE DATE WAS 10/19/07, THEY DID NOT MEET THAT COMPLIANCE DATE. THERE ARE TREE WELL HOLES IN THE PARKING AREA WHERE PUBLIC IS PARKING THAT NEED TO BE BARRICADED - NOT DONE AS OF MONDAY 10/22/07
10/18/2007 ENGINEERING - FINAL Correction Required TEMP C OF O GIVEN BY BLDG. OFFICIAL WITH AGREEMENT AND A SCHEDULE FOR COMPLETION:

A) NO CONSTRUCTION PARKING IN PARKING LOT DURING TEMP C OF O -- NOT COMPLYING AS OF 10/18/07
B) ALL CONSTRUCTION ACTIVITY SEPARATE FROM OCCUPANTS -- NOT COMPLYING AS OF 10/18/07.

10/9/07 -- (1) FENCE CONSTRUCTED TO ISOLATE EAST END OF PARKING LOT.--- COMPLETED

ALL OTHER ITEMS LISTED ON THE SCHEDULE FOR COMPLETION LETTER REGARDING A TEMP C OF O, (2 THRU 6) HAVE NOT BEEN COMPLETED AS OF 10/18/07. NOTIFIED SUPERINTENDENT (JERRY HENDRIX) OF COMPETION TIMELINE, HE STATED THAT ALL ITEMS WILL BE COMPLETED BY TOMORROW 10/19/07.
10/09/2007 ENGINEERING - FINAL Denied IN ADDITITON TO THE ITEMS LISTED ON THE 10/03/07 THAT HAVE NOT BEEN ADDRESSED, PROVIDE ADEQUATE PARKING FOR OCCUPANTS,(NUMBER OF SPACES/OCCUPANCY). ENSURE PARKING FOR OCCUPANTS IS SEPARATE FROM CONSTRUCTION VEHICLES AND EQUIPMENT.

IN ADDITION, FINAL GRADING FOR PERMIT #T06BU01543, SITE WORK, AND CHANGE MADE TO TRASH ENCLOSURE MUST BE COMPLETED PRIOR TO C OF O FRO ENGINEERING APPROVAL.
10/03/2007 ENGINEERING - FINAL Denied 1) COMPLETE SITE WORK PER YOUR APPROVED SITE PLAN.
2) CLOSE OUT GRADING PERMIT. CALL IN FOR FINAL GRADING INSPECTION FOR PERMIT # T06BU01543.
3) SEPARATE ALL CONSTRUCTION ACTIVITY FROM PUBLIC ACCESS.
4) SEPARATE ALL CONSTRUCTION MATERIAL AND EQUIPMENT FROM PUBLIC.
5) PROVIDE A SAFE ENVIRONMENT FOR BLDG OCCUPANTS.
6) COMPLETE TRASH ENCLOSURE PER APPROVED PLAN.
7) PROVIDE PARKING FOR OCCUPANTS.