| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) THIS COMPLETES THE UNDERGROUND 2) OK TO COVER ALL AREAS |
|
| 06/16/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. REDLINE CHANGES TO THE PLAN IN RED 2. CONTRACTOR TO REDLINE ALL CHANGES PRIOR TO INSPECTION. 3. ABS UNDERGROUND AT #102, 103 ALSO, #803, 804 OK TO COVER |
|
| 06/01/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* GAS PIPING STILL DISASSEMBLED. |
|
| 05/07/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. NEW 4" ABS SEWER AS INSTALLED PER REDLINES FOR BLDG'S #600, #700, #800, #900-#100-200, 300, 400, 500 STUB UPS FROM MAIN ONLY. TO P.O.C AT EXISTING WATER TEST OK OK TO COVER. 2. 2" COPPER YARD WATER FROM RPPBP PLUS OR MINUS EIGHTY FEET TO FIRST BRANCH OK TO COVER. |