Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/11/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 01/09/2006 | PLUMBING - ROUGH, SOIL | Cancelled | CANCELLED PER AURA #954-1345 | |
| 01/09/2006 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NO WATER IN 10' HEAD TEST 2) PLAN AND PERMIT NOT ON SITE-PLUS #1-3 ABOVE |
|
| 01/06/2006 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NEED PLAN AND PERMIT ON SITE 2) NEED 10' HEAD TEST ON ALL NEW ROUGH PLUMBIN |
|