Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/25/2007 | ENGINEERING - FINAL | Approved | ||
| 09/29/2006 | ENGINEERING - FINAL | Partial Approval | OK FOR TEMPORARY C OF O. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 IS COMPLETED AND APPROVED. 1. PROVIDE TEMPORARY CONSTRUCTION FENCE AROUND NORTH BUILDING AND ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING TO PREVENT PUBLIC/PEDESTRIAN ACCESS. 2. PROVIDE TEMPORARY PEDESTRIAN WALKWAY WITH RAMPS AND TRUNCATED DOMES TO THE PUBLIC R.O.W. NEAR THE NORTHEAST CORNER OF THE SITE. 3. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS, AND RE-LOCATE PORTA-TOILETS. 4. ADDRESS PONDING WATER IN FRONT OF TRASH ENCLOSURE AND VERIFY APPRORIATE SIZE OF ENCLOSURE.. |
|
| 09/28/2006 | ENGINEERING - FINAL | Denied | 1. PROVIDE A LETTER OF CERTIFICATION FROM THE AZ REGISTERED P.E THAT CERTIFIES THAT THE SITE WORK AND DRAINAGE IMPROVEMENTS WERE CONSTRUCTED IN CONFORMANCE WITH THE C.O.T. APPROVED PLANS AND WILL FUNCTION AS DESIGNED. 2. PROVIDE CONSTRUCTION FENCE OR APPROPRIATE BARRICADING TO PREVENT PUBLIC/PEDESTRIAN ACCESS TO ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING. 3. PROVIDE TEMPORARY PEDESTRIAN WALKWAY AND RAMPS TO THE PUBLIC R.O.W. 4. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. |
|
| 09/27/2006 | ENGINEERING - FINAL | Denied | NOT READY FOR INSPECTION |