Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/11/2007 | PLUMBING - PROGRESS | Approved | ||
| 11/22/2006 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* 1) OFF SET EXPANSION LOOPS AT 30' INTERVALS AS DISTALLED BY SWAON ON 11/20/06. APPEARS TO MEET UPC REQUIREMENTS. EXPANSION COUPLINGS IF LISTED FOR SUCH USE. HAVE PLAN REVISION APPROVED BY CITY OF TUCSON |
|
| 10/05/2006 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 10/02/2006 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 09/29/2006 | PLUMBING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* |