Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/07/2006 | FRAMING | Approved | IVRS - Inspection :* | |
| 07/05/2006 | FRAMING | Denied | IVRS - Inspection : A reinspection fee has been assessed for this inspection. Multiple inspection C02BU truss not bearing at mid-point Refee |
|
| 06/30/2006 | FRAMING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. C02 BV TRUSS NOT BEARING AT MIDPOINT |
|
| 06/23/2006 | FRAMING | Denied | IVRS - Inspection : Work is not complete enough to inspect.| 950* 1) THIS HOUSE HAS BEEN FRAMED WITH UNDER SIZED FASTENER STUDS REQUIRE 2-16D NAILS WHEN FACE NAILED TO PLATES AND 3" X .131 10D NAILS HAVE BEEN USED. YOU MUST HAVE ENGINEER OF RECORD ? STRUCTURE AND REPORT TO CITY OF TUCSON WITH RECOMMENDATION AND REPAIR 2) PLANS CALL FOR GAS PIPING. YOU MUST EITHER INSTALL GAS LINES PER PLAN OR HAVE GAS LINES REMOVED FROM PLANS AND PERMIT 3) FIRE STOPS REQUIRE 2 LAYERS OF 1/2" OSB 4) WIRES MUST TERMINATE IN APPROVED ELECTRIC BOXES 5) DUCT WORK OUT OF KITCHEN WALL 6) RED HEAD ANCHOR BOLTS LOOSE 7) MASTER BATH WALL NOT ANCHORED 8) C02BV TRUSS NOT BEARING MID POINT 9) STOPPED INSPECTION-TOO MANY ITEMS |