Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 06/30/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SIDEWALKS & LIGHT POLES OK |
|
| 06/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 06/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OUTDOOR CHAPEL OK TO POUR | |
| 06/09/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* OUTSIDE CHAPEL FOOTERS ONLY |
|
| 04/04/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 4 @ COLUMN FOOTINGS @ NORTH PATIO |
|
| 03/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTINGS FOR NORTH COURTYARD SITE WALL |
|
| 03/01/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) FOOTINGS NEED TO BE FREE OF DEBRIS 2) VERIFY SIZE AND AMOUNT REINFORCEMENT FOR FOOTINGS. PROVIDE STAMPED LETTER FROM ENGINEER. DETAIL 10 ON SHEET S4 DOES NOT SPECIFY 3) NEED TO RELOCATE GAS LINE IF APPLICABLE/RESOLVE GAS LINE ISSUE 4) NEED #5 VERTICAL REINFORCEMENT AT JAMBS PER SCHEDULE ON SHEET S6. PLEASE FIND OUT FROM ENGINEER IF ADDITIONAL #5 VERTICAL REBARS ARE REQUIRED AT WEST GATE IF LARGER THAN 8' |