Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2006 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 05/16/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 05/15/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* - DWV AND WATER PIPING IN ROOMS 142A, 148, 138 AND 140 - WATER PIPING W/50 PSI STREET PRESSURE. - NOTE: NON-FERROUS PIPE NIPPLES REQUIRED FOR STUB-OUTS |
|
| 05/12/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 05/03/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. ROOMS #130, #131, #132, #106, #146 & ALONG CORRIDOR 110 OK TO INSULATE DWV OK OK TO COVER AFTER HOT INSULATED |
|
| 04/20/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. PRE-CON MEETING MATERIAL STAGED ON SITE OK 3. PLEASE RECALL WHEN STARTS INSTALLING. |
|
| 04/19/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1/2" CAPPED TUBING ON STRUT TRAPPEZE HANGERS 4 ZONE BOXES INSTALLED - NOT CONNECTED HAS NOT STARTED TO BRAZE PROGRESS LOOKS GOOD BUT RECALL SO RICK CAN INSPECT |
|
| 04/14/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. INSULATION 2ND FLOOR OK |
|
| 04/13/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OK TO COVER SECOND FLOOR |