Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2006 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* | |
| 05/16/2006 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1. SEAL 3/4" OPENING AT TOP OF PANEL WHERE #4 COPPER ENTERS PANEL. 2. INSTALL PANEL SCHEDULE. 3. PROVIDE LIGHTING PLAN. |
|
| 05/15/2006 | ELECTRIC - FINAL | Partial Approval | 5:00 AM (5-15-06) SCHEDULED AFTER HOURS INSPECTION FIELD COLLECTED $108.00 CHECK #11442 JP TUCKER CONST. INC. OK SERVICE WORK TEP ENERGIZED EQUIPMENT (NO CLEARANCE REQ'D) |
|
| 05/04/2006 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 05/03/2006 | ELECTRIC - FINAL | Denied | IVRS - Inspection : The service is not per code.| 210* SERVICE INSPECTION ONLY 1. NEED BUSHINGS FOR #4 AND LARGER CONDUCTORS NEC 300 2. IDENTIFY GROUNDED CONDUCTOR NEC 200. 3. BOND SERVIE RACEWAY NEC 250 4. GROUNDED CONDUCTOR AND BONDING CONDUCTOR RUN PARALLEL AND WILL HAVE OBJECTIONABLE CURRENT ON BONDING CONDUCTOR NEC 250.6 5. NEED MINIMUM #4 CU BONDING CONDUCGTOR FOR SERVICE NEC 250.66 6. MAKE UP A PHASE SO YOU DON'T HAVE EXCESS CONDUCTOR IN METER NEC 110. 7. INSTALL ADDRESS ON SERVICE, INSTALL L.B COVER. 8. IDENTIFY SERVICE DISCONNECT NEC 230 |