Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T05CM05399

Parcel: 11304104E

Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Date Description Inspector Results Comments
04/03/2006 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
CLOSET FLANGES SECURED W/BRASS SCREWS OK
TEST ON TUB & SHOWER DRAINS OK
03/31/2006 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
- HOSE BIBB VACUUM BREAKERS ARE REQUIRED FOR CONSTRUCTION HOSE BIBBS.
- INSTALL VAC. BREAKER ON TEMPORARY HOSE BIBBS AND ANY OTHER LOCATION THAT IS BEING USED DURING CONSTRUCTION.
- FILL TUBS AND SHOWER TO FLOOD RIM TO TEST WASTE AND OVERFLOW CONNECTIONS.
- FASTEN CLOSET FLANGES TO FLOOR ON GROUND LEVEL, USE BRASS OR EQUALLY CORROSION RESISTANT ANCHORS.
- OK TO COVER ALL AREAS EXCEPT UNDER TUBS & SHOWERS.
03/30/2006 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1. ABS DWV IS TO BE SUPPORTED AT EACH CHANGE OF DIRECTION OR ELEVATION, AND AT THE END OF BRANCHES, THEN EVERY FOUR FEET BETWEEN HANGERS.
2. TRAP ARMS ARE TO BE SUPPORTED AS CLOSE TO THE TRAP AS POSSIBLE.
3. MINIMUM SIZE WASTE PIPING FOR BATHTUB/SHOWER IS TWO INCH. THE TRAP ARM MAY BE INCH AND A HALF.
BACKPITCHED SECTIONS OF WASTE OR VENT TO BE CORRECTED.
03/21/2006 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*