| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2005 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
|
| 12/08/2005 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* 1) SECURE UNIT NUMBERS TO EQUIPMENT 2) AC-2 STILL NOT FUSED CORRECTLY AND STILL HAS CONDENSATE TERMINATED INTO SEWER VENT 3) STILL NO PERMIT FOR NEW AC 4) EXISTING CONDENSATE DRAINING ON ROOF 5) REPAIR SEAL TITE ON AC-3 6) VENTS ON CONDENSATE DRAINS MUST BE DOWN STREAM OF TH TRAP 7) OK TEMP C OF O |
|
| 12/06/2005 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* 1. PROVIDE NUMBERS TO I.D. ROOFTOP UNITS 2. NEW 24,000 BTUH UNIT (RHEEM) NE CORNER A. UNIT IMPROPERLY FUSED B. CANNOT TERMINATE NEW UNIT INTO SEWER WASTE VENT 3. BLOCK/CLAMP ALL ROOF TOP GAS LINES AS NECESSARY. 4. IS NEW UNIT PERMITTED - APP. PLAN SAYS ALL EXIST A/C ARE USED, NONE NOTED NEW |