Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2007 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 05/02/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 18 FOOTING FOR SWIMMING POOL FENCE |
|
| 04/04/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. LIGHT OR LIGHT FOOTINGS POST, REGARDING DETAIL ON SHEET A0.4 10' DEPTH, 18" WITH A #5 VERT. W #3 @ 12" O.C HORIZONTAL |
|
| 03/06/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 2 PATIOS ON SOUTHSIDE OF THE BUILDING, INCLUDED VERIFICATION ON OR FOR STORAGE BUILDING. |
|
| 03/01/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NORTH SIDE 2 PATIOS AND ENTRY WEST ENTRY EAST SIDE 2 FIRST PATIOS ON NORTH SIDE PLUS ENTRY 2 FIRST PATIOS FROM SOUTH SIDE |
|
| 02/23/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PATIO FOOTING @ N AND SE |
|
| 02/15/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ELEVATOR LOBBY BRIDGE CONT. FOUNDATION 1/S3.0 CORRIDOR GRIDLINE 33'2" EAST EXTERIOR FOOTING CONT. 1/S3.0 |
|
| 02/13/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* EXTERIOR WALL FOR LOUNGE, LOBBY RESTROOMS, SALES CENTRAL MANGER ROOMS. EAST WALLS 34', 16'4", 25' 11 1/4" MAIN BUILDING WEST WALL 88' PLUS STAIRS AREA INCLUDED ROOMS 100-105 |
|
| 02/09/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 02/08/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 02/07/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 02/05/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR PIT STEM WALL 48" DETAIL 8 ON SHEET S3.0 2) GATE HOUSE PERIMETER WALL SOUTH 65'-1", WEST 122'-10 3/4", PLUS 39'-4 3/4", NORTH 8'-9 1/4" AND EAST 44'-0" |
|
| 01/31/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PERIMETER FOOTINGS GRIDLINE WEST 21'-0" NORTH 48'-0" WEST 128' EAST 176' |
|
| 01/30/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* WEATHER CONDITIONS, NOT COMPLIANCE WITH SECTION 1802 & 1805.4.2.3 REGARDING CONCRETE FOOTINGS SHALL NOT BE PLACED THROUGH WATER. |
|
| 01/29/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GRIDLINE: SOUTH PERIMETER FOOTING EAST 117'0" ELEVATOR PIT FOOTING |
|
| 01/19/2007 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED BY GENERAL CONTRACTOR EBCO | |
| 01/18/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NOTE: INSPECTION COVER THE FOLLOW SECTION ON FOUNDATION PLAN SHEET S1.0 GRIDLINE: EAST 121'-0" NORTH 56' - 0" WEST 121'-0" DETAIL 1 ON SHEET S3.0 |