Permit: T05CM05116

Parcel: 11446019D

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
01/05/2007 ENGINEERING - FINAL Approved SEE ATTACHED ENGINEER'S CERTIFICATION LETTER FROM KEVIN M. HALL
12/29/2006 ENGINEERING - FINAL Denied ITEMS #1 AND #2 HAVE BEEN COMPLETED AT THIS TIME.
3) INSTALL ALL BIKE RACKS AS SHOWN ON THE APPROVED PLANS, THIS INCLUDES ATTACHING THEM TO THE SUBSTRUCTURE.
4) BACKFILL THE NEW 6" CURB.
5) CLEAN ALL SILT MATERIAL FROM THE BASIN.
6) PROVIDE CERTIFICATION LETTER FOR ALL DRAINAGE ASPECTS OF THIS PROJECT.
12/13/2006 ENGINEERING - FINAL Denied 1. PROVIDE TRUNCATED DOMES ON THE PEDESTRIAN ACCESS ROUTE FROM TANQUE VERDE ROAD AS SHOWN ON THE PLAN.
2. CONSTRUCT DRAINAGE SWALE ON EAST SIDE OF THE BUILDING TO THE R/D BASIN AT THE NE CORNER OF THE SITE AS SHOWN ON DETAIL C-C OF THE SITE PLAN.
3. PROVIDE (3) CLASS I AND (4) CLASS II BICYCLE PARKING SPACES AT THE NW CORNER OF NEW BUILDING AND SW CORNER OF THE EXISTING BLDG. AS SHOWN ON THE PLAN.
4. PROVIDE 6" REVEAL CURB AT THE SE CORNER OF THE SITE.
5. CLEAN UP AND RE-ESTABLISH GRADE IN THE RETENTION BASIN THAT WAS DISTURBED BY CONSTRUCTION.
6. PROVIDE A LETTER OF CERTIFICATION FROM AZ REGISTERED P.E. THAT CERTIFYS THAT THE SITE WORK WAS CONSTRUCTED IN CONFORMANCE WITH THE APPROVED PLANS.