| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2006 | EXT METAL CLIPS/EXT SHEATHING | Approved | IVRS - Inspection :* | |
| 03/01/2006 | EXT METAL CLIPS/EXT SHEATHING | Partial Approval | IVRS - Inspection :* 1) EXCEPT PORCH CORBEL DETAIL 10/5 |
|
| 02/28/2006 | EXT METAL CLIPS/EXT SHEATHING | Not ready for Inspection | IVRS - Inspection :* 1) CANCELLED BY SUPER |
|
| 02/27/2006 | EXT METAL CLIPS/EXT SHEATHING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) COMPLY WITH DETAIL 1/5 80 AT 6" ON CENTER AT TRUSS BLOCKING 2) REFEE |
|
| 02/22/2006 | EXT METAL CLIPS/EXT SHEATHING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) COMPLY WITH NOTE 4 FROM PREVIOUS INSPECTION 2) COMPLY WITH NOTE 5 3) COMPLY WITH NOTE 7 & 8 |
|
| 02/14/2006 | EXT METAL CLIPS/EXT SHEATHING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) COMPLY WITH PREVIOUS INSPECTION |
|
| 02/13/2006 | EXT METAL CLIPS/EXT SHEATHING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) TO MUCH DEBRIS ON ROOF 2) PROVIDE 18" GAP ALL OSB ENDS AND JOINTS 3) PER TRUSS CALCS DBL TOP PLATES REQUIRED AT MID BEARING C1 AND C2 TRUSSES FOR 3 POINT BEARING TRUSSES 4) PER DETAIL 1/5 NAIL 2 X 8 BLOCKS 6" ON CENTER THROUGHOUT 5) INSTALL H2.5 EACH STUD PER DETAIL 12/5 6) NAIL ALL JOINTS 1/5 EAST WALL 6" ON CENTER AND SOUTH WALL 7) DETAIL 10/5 CENTER POST LAG BOLT INTO CORBEL ? 8) INSTALL H2.5 PER DETAIL 8/5 |
|
| 02/09/2006 | EXT METAL CLIPS/EXT SHEATHING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) GATES LOCKED-UNABLE TO ENTER |