Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T05CM04860

Parcel: 11202034A


Addresses:

3838 N CAMPBELL AV


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T05CM04860

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
02/22/2007 ENGINEERING - FINAL Approved SEE INSPECTION RESULTS FOR PERMIT #T05BU01167
02/15/2007 ENGINEERING - FINAL Partial Approval 3 ITEMS HAVE BEEN ADDRESSED THAT WERE IDENTIFIED ON THE 2/6/07 FINAL GRADING INSPECTION:
1) FILTER FABRIC HAS BEEN ADDED TO THE ROCK SCOUR PAD LOCATED AT THE OUTLET PIPE OF THE CATCH BASIN.
2) CONSTRUCTION OF THE SWALE ADDED AT THE 6' CURB OPENING ALONG THE NORTH SLOPE HAS BEEN COMPLETED.
3) ALL TEMP STORM WATER CONTROLS HAVE BEEN REMOVED EXCEPT FOR 10' OF WADDLE AT CURB OPENING ON NORTH SIDE.

OK FOR TEMP C OF O. PERMANENT C OF O WILL NOT BE APPROVED UNTIL THE FINAL GRADING FOR PERMIT # T05BU01167 HAS BEEN COMPLETED AND APPROVED
02/06/2007 ENGINEERING - FINAL Partial Approval FINAL GRADING NOT COMPLETED AND APPROVED.
OK TO EXTEND TEMP C OF O.
01/05/2007 ENGINEERING - FINAL Partial Approval PER INSPECTION SHEET OKAY BY MRUSSO FOR TEMP C OF O
1/3/07
01/04/2007 ENGINEERING - FINAL Partial Approval TEMP C OF O ONLY, PERMANENT C OF O NOT TO BE GIVEN UNTIL:

1) SITE WORK IS COMPLETED TO INCLUDE THE DRAINAGE CHANNEL AND OUTFALL LOCATED ON NORTH SIDE OF SITE.
2) A COMPLETED AND APPROVED FINAL GRADING INSPECTION FOR PERMIT# T05BU01167 IS DONE.
3) COMPLETE LANDSCAPING AND REMOVE ALL SEDIMENT CONTROLS, CONSTRUCTION EQUIPMENT AND DEBRIS.
01/03/2007 ENGINEERING - FINAL Partial Approval
12/04/2006 ENGINEERING - FINAL Partial Approval TEMP ONLY, PERMANENT C OF O NOT TO BE GIVEN UNTIL SITE WORK IS COMPLETED PER THE APPROVED GRADING PLAN AND THE FINAL GRADING INSPECTION FOR PERMIT #T05BU01167 IS COMPLETED AND APPROVED.
11/08/2006 ENGINEERING - FINAL Partial Approval PARTIAL APPROVAL FOR TEMP C OF O FOR ENGINEERING
ONLY.PERMANENT C OF O NOT TO GIVEN UNTIL A FIANL GRADING INSPECTION FOR PERMIT # T05BU01167 IS COMPLETED AND APPROVED.
10/19/2006 ENGINEERING - FINAL Denied DENIED, SITE NOT READY
10/18/2006 ENGINEERING - FINAL Denied Contractor needs to:
1- Contractor needs to complete all work on the phased plan.
2- Also complete punch list from 10/11/06 and 10/05/06.
3- Provide stormwater controls for outfall on northeast corner of project.
4- Keep driveway to the north of project clean of silt.
5- Provide letter from engineer in regards to to drainage cert. Per chapter XIV, section 14.2 (7), for final C of O.
10/16/2006 ENGINEERING - FINAL Denied NOT READY SEE 10-11-06 INSPECTION COMMENTS
10/11/2006 ENGINEERING - FINAL Denied PRIOR TO APPROVAL FROM ENGINEERING FOR A TEMPORARY C OF O FOR STAFFING AND STOCKING ONLY (NO PUBLIC ACCESS), COMPLETE THE FOLLOWING IN THE AREA THAT IS FENCED IN:

1) COMPLETE THE SIDEWALK ALONG THE SE CORNER OF BLDG OR FENCE AROUND IT.
2) LIMIT HEAVY EQUIPMENT IN THE OCCUPIED AREA.
3) COMPLETE OVERHEAD WORK FOR AWNING AT SOUTH ENTRANCE.
4) COMPLETE CURBING IN PARKING AREA.
5) COMPLETE SIDEWALK AT WEST ENTRANCE/EXIT AND FENCE IT.
6) COMPLETE PAVING AT NW CORNER FOR TRASH/LOADING ACCESS.
7) REMOVE ALL CONSTRUCTION DEBRIS AND MATERIAL FROM WITH IN FENCED AREA.
8) ALL ENTRANCES/EXITS MUST BE ADA COMPLIANT.
10/05/2006 ENGINEERING - FINAL Denied PRIOR TO APPROVAL FROM ENGINEERING FOR A TEMPORARY CERTIFICATION OF OCCUPANCY, COMPLETE THE FOLLOWING:
1) COMPLETE PAVING AND STRIPING.
2) PROVIDE UNRESTRICTED ADA COMPLIANT ACCESS FOR OCCUPANTS.
3) COMPLETE DRAINAGE STRUCTURE TO ALLOW FOR CONTROL OF STORM WATER (SCUPPERS, CATCH BASINS, RET/DET BASINS ETC.).
4) INSTALL EXTERIOR LIGHTING.
5) PROVIDE TRASH DISOSAL/SERVICE ACCESS.
6) ENSURE NO LIFE/SAFETY CONDITIONS EXIST.
7) SEPARATE ONGOING CONSTRUCTION ACTIVITY FROM PUBLIC.
8) SUBMIT TEMP C OF O PHASING PLAN W/ C OF O APPLICATION TO THE BUILDING OFFICIAL.
10/02/2006 ENGINEERING - FINAL Not ready for Inspection SITE NOT READY FOR INSPECTION

OKAY FOR TEMP C OF O PER MRUSSO