Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2006 | FRAMING | Approved | IVRS - Inspection :* | |
| 01/18/2006 | FRAMING | Cancelled | CANCELLED PER TIM OF K.B. HOMES #907-6040 | |
| 01/17/2006 | FRAMING | Denied | IVRS - Inspection : Work is not complete enough to inspect.| 950* 1) RED HEAD ANCHOR BOLTS LOOSE 2) NO DWV WATER TEST 3) LEAK AT KITCHEN 4) TRUSSES NOT BEARING 5) STOPPED INSPECTION-HOUSE NOT READY 6) NEXT FAILURE WILL BE CHARGED A REINSPECTION FEE |
|
| 01/13/2006 | FRAMING | Denied | IVRS - Inspection : Work is not complete enough to inspect.| 950* 1) RED HEAD ANCHOR BOLTS LOOSE 2) SEAL SECOND FLOOR PENETRATIONS 3) HOLDOWNS MISSING 4) WALLS REQUIRING ANCOR BOLTS AT 16" ON CENTER NOT DONE 5) HOUSE NOT COMPLETE ENOUGH TO INSPECT 6) STOPPED INSPECTION |