Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* PIPE WRAPS & TAPE PRIMERS OK NOTE: 2" DRAIN TO SUMP SHOULD BE A HORIZONTAL TERMINATION INTO SUMP PIT. |
|
| 04/26/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* UNDERGROUND WASTE & VENT WATER TEST THRU BUILDING & 2-WAY CLEANOUT CAPPED OK 1 1/2 SUMP DRAIN FROM SUMP TO BUILDING EXTERIOR WATER TEST OK 2-1" CW LOOPED UNDER SLAB TO FOUNTAIN & PLANTER OK 1. CALL FOR PIPE WRAP INSPECTION PRIOR TO CONCRETE. |
|
| 04/11/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 2" DRAIN TO SUMP PIT WATER TEST OK |