Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2008 | ENGINEERING - FINAL | Approved | ||
| 12/04/2007 | ENGINEERING - FINAL | Correction Required | TALKED WITH GENERAL CONTRACTOR, APPROVED A LANSCAPE DESIGN TO ALLOW FOR WATER HARVESTING IN ALL LANDSCAPE AREAS. CALL FOR INSPECTION WHEN COMPLETED. | |
| 11/29/2007 | ENGINEERING - FINAL | Correction Required | SPOKE WITH THE GENERAL CONTRACTOR (TPD BUILDERS TOM AND TOM BAILEY 909-1495/770-0846/403-6901) TO DISCUSS THE DRAINAGE PROBLEM AND POTENTIAL FLOODING ASSOCIATED WITH CONSTRUCTION OF NEW TOWNHOMES. RECOMMENDED THAT THEY INSTALL 6" WATER HARVESTING AREAS AROUND ALL LANDSCAPING AS SHOWN ON THE APPROVED PLAN. ALSO RECOMMEND THEY PLACE GRAVEL ON THE ALLEY WAY AND GRADE TO PRE-CONSTRUCTION CONDITION. |