Permit: T05CM04310
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2006 | ENGINEERING - FINAL | Approved | ||
| 07/20/2006 | ENGINEERING - FINAL | Partial Approval | OK FOR 30 DAY EXTENSION OF THE TEMPORARY C OF O . 1. COMPLETE SITE WORK IDENTIFIED ON THE 5/10/06 INTERMEDIATE GRADING INSPECTION OF "INFORMAL" PHASE I, THAT INCLUDED LOTS 15-23 AND 38-49. 2. CONSTRUCT VERTICAL CURB AT HANDICAP PARKING TO DETAIL I SPECIFICATIONS. 3. PROVIDE 6" STORMWATER HARVEST AREAS IN MEDIAN ISLANDS AS SHOWN ON THE PLAN. KEYNOTE 27. 4. PROVIDE BICYCLE PARKING AT (9) LOCATIONS AS SHOWN ON THE PLAN. 5. PROVIDE A CERTIFICATION LETTER FROM THE ENGINEER THAT CERTIFYS THE ENTIRE PROJECT. |
|
| 04/13/2006 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED 1. COMPLETE ALL PUNCHLIST ITEMS ON PREVIOUS INSPECTION REPORT. 2. BARRICADE ALL AREAS ADJACENT TO THIS BUILDING WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING TO PREVENT PEDESTRIAN/PUBLIC ACCESS. 3. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 4. CONSTRUCT SOLID WASTE/TRASH ENCLOSURES TO THE APPROVED PLANS SPECIFICATIONS. |
|
| 04/10/2006 | ENGINEERING - FINAL | Denied | NOT READY 1. PREPARE A PHASED SITE PLAN AND CALL 419-2466. 2. PROVIDE A LETTER OF CERTIFICATION FROM AN AZ REGISTERED P.E. STATING THAT THE PROJECT, R/D BASIN, AND THE DRAINAGE SYSTEM ARE CONSTRUCTED IN SUBSTANTIAL CONFORMANCE WITH THE PLAN AND WILL FUNCTION AS DESIGNED 3. COMPLETE PEDESTRIAN WALKWAYS AND SIDEWALK (ACCESSIBLE ROUTES) 4. PROVIDE HANDICAP PARKING, SPACES, SIGNS AND RAMPS THAT CORRESPOND TO THE DEVELOPMENT PLAN AND SITE PLAN. 5. DEPRESS LANDSCAPE AREAS AND PARKING ISLANDS 6" FOR STORMWATER HARVESTING. 6. PROVIDE TRUNCATED DOMES AT HANDICAP RAMPS OR WHERE PEDESTRIAN ACCESS ROUTES INTERSECT DRIVEWAYS OR PARKING AREAS. 7. SIDEWALK WIDTHS SHALL CORRESPOND TO PC/COT STANDARD DETAIL 200. 8. PROVIDE 24' PAAL NORTH OF BUILDING. |