Permit: T05CM03937

Parcel: 12901044C


Addresses:

1940 E BROADWAY BL


Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Permit Number - T05CM03937

Inspection Description - PLUMBING - ROUGH, SOIL

Inspection Status - Approved

Date Description Inspector Results Comments
01/10/2007 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
12/05/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
10/13/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. GREASE TRAP PIPING TEST OK
2. HCS TIE INS TEST OK
3. MEZZANINE PIPING IN WALL OK
4. HAND IN PHARMACY TEST OK
10/02/2006 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
CALL FOR YARDWATER AND HAVE DRAWINGS REDLINED.
09/25/2006 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
PRE-SLAB STARBUCKS AREA OK PENDING REVISED APPROVED PLAN FROM CITY -- COVER AT OWN RISK.
09/22/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. STARBUCKS NEEDS TO HAVE APPROVAL PLANS FOR CHANGES UNDERGROUND GROUND OK PER PLANS TATE ARE NOT APPROVED.
2. BAKERY WALL VENTS & WATER PIPING OK
08/24/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
3" WATER MAIN SOUTH SIDE ON TEST 3' UP WALL AND 5' OUT FROM BUILDING TEST OK
08/11/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
08/10/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
08/07/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. EAST OF PRODUCE BOX MAIN OK
2. MEAT & SEAFOOD PUMP TO ICE CREAM FREEZER OR MAIN
08/03/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
MEAT DEPT.
08/02/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. PARTIAL ON (FLORAL TO PRODUCE) UNDERGROUND AIR TEST OK DUE TO RAIN.
2. RESTROOMS #118 JAN. CLOSET #120 UNDERGROUND AIR TEST OK DUE TO RAIN
3. RECEIVING #116 UNDERGROUND AIR TEST
08/01/2006 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
07/29/2006 PLUMBING - ROUGH, SOIL Not ready for Inspection CHECK #8607
RAINOUT
07/25/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
CONTINUATION OF 4" GREASE WASTE FROM 7/18/06 WEST TO SEAFOOD/MEAT INCLUDING FLOOR DRAIN (4) FD-4 TO INITIAL 7/24/06 WATER TEST (PARTIAL) REPAIR LEAK ON 3" TO SEAFOOD FS-4 APPROX. 15' FROM 4" FCO AT WEST END.
07/24/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
4" SANITARY DRAINAGE FROM STUB UP AT MEZZANINE THRU STARBUCKS THRU RESTROOM AREA, DELI, TIE IN FOR DAIRY CASES COMBINATION WASTE & VENT, BAKERY WATER TEST TO EXTERIOR OF BUILDING, 2-WAY CLEANOUT OK
1. PLAN IS APPROVED IN ERROR HANDSINK IN STARBUCKS REQUIRES DIRECT DRAINAGE CONNECTION.
2. 4" STUB UP FOR CONTINUATION OF SANITARY AT SOUTHEAST CORNER FOR CONTINUATION OF SANITARY TO WEST BUILDING.
3. 3-COMP SINK IN STARBUCKS SHOULD REQUIRE WASH/RINSE TO GO DIRECT DRAINAGE; SANITIZE TO INDIRECT.
07/21/2006 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
07/19/2006 PLUMBING - ROUGH, SOIL Partial Approval INSTALL OF ? ON COMBINATION WASTE AND VENT SYSTEM TAIL PIECES FOR FLOOR SINK IN DAIRY CASE AREA WATER TEST OK
07/18/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
CONTINUATION OF 4" GREASE WASTE FROM 7/13/06 INSPECTION TURNS SOUTH THRU EXTERIOR APP. 40' WITH COMBO TO CONTINUE TO WEST. WATER TEST OK MY INITIAL ON P1.1
4" SANITARY STUB 15' INTO BUILDING AT SOUTHEAST CORNER TO 6" BUILDING SEWER 40' OUT OF BUILDING INCLUDING 4" COMBO UP FOR FLOOR SINK. WATER TEST OK.
4" COMBINATION WASTE & VENT FOR DAIRY CASES FROM MY INITIAL P1.1 BACK UPSTREAM THRU VENTS TO F.F WATER TEST PARTIAL.
1. SHALL INSTALL REDUCER AT P-TRAP FOR TAILPIECES TO FIXTURE WITH RETEST.
2. ALL SHADING TO BE GOOD MATERIAL 1/2" MINUS.
07/13/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
4" GREASE WASTE FROM DELI THRU BAKERY TO JUST BEFORE FCO TO EXIST BUILDING MY INITIAL ON P1.1 IN TRAILER WATER TEST OK
07/12/2006 PLUMBING - ROUGH, SOIL Cancelled IVRS - RI canceled