Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T05CM03677
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/23/2005 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
09/22/2005 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) MOVE STHDIO? AT GARAGE FRONT TO 6" WALL PORTION 2) MISSING 5/8 8" CONE? DIAGONAL BAR |
|
09/21/2005 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) CRUMB OUT LEVEL FTG. BOTTOMS 2) UFER NOT INSTALLED 3) PLUMB PREP NOT DOME 4) 8' DIAGONAL BAR MISSING 5) GARAGE P.S. TO BE IN 6" WALL NOT 4" |
|
09/19/2005 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) GARAGE FOOTINGS REQD 2' BELOW TOP OF SLAB PER 202/SD 2) FOOTINGS REQD FOR INTERIOR HOLDDOWNS <B> AND <M> PER 209/SD 3) REBAR MUST HAVE 3" CLEARANCE TO SOIL 4) 203/SD MIN 4" TOP OF SLAB TO TENDON |