Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2006 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 09/27/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* PROVIDE METHOD OF MAINTAINING TRAP SEAL OF FS'S INTALLED TO RECEIVE CONDENSATE ONLY, SEE INSPECTION NOTES FROM 5/1/06 CALL FOR INSPECTIONS NOT YET APPROVED. |
|
| 07/13/2006 | PLUMBING - INTERMEDIATE | Partial Approval | WATER TEST NORTHWEST FLOOR SINK THRU ROOF PROVIDE REVISED APPROVED PLAN OF ADDITION OF NORTHEAST FLOOR SINK AND REVISED APPROVED GAS PIPING PLAN PER YOUR INSTALLATION. GAS PIPING & METER NOT INSTALLED PER PLAN. |
|
| 12/16/2005 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4" RD AND 4" ORD AT SOUTH EAST CORNER WATER TEST OK TO 2' OUTSIDE OF BLDG 2) 6" RD AND 6" ORD AT SOUTH WEST CORNER WATER TEST OK TO POINT OF EXISTING UNDERGROUND OK |
|
| 12/15/2005 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER TEST 6" RD AND 6" ? AT SOUTH EAST CORNER TO POINT OF CONNECTION TO EXISTING OK |