Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2008 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 09/17/2008 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* 1. PROVIDE FUSES IN ELEC. DISCONNECT AND PROPERLY CONNECT CONDUCTORS. 2. RELOCATE DISCONNECT TO ALLOW ROOM FOR GREASE RECEPTOR. 3. SECURE WATER LINE TO BLOCK ON ROOF. 4. PROVIDE A THERMOSTAT FOR DUCT HEATER. |
|
| 08/28/2008 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* 1. PROVIDE GUARD RAILS AT EQUIPMENT WITHIN 10' OF EDGE OF ROOF 2. PROVIDE A GREASE CUP ON EXHAUST FAN 3. EXTEND SEWER VENT MIN. 2' ABOVE EVAP. COOLER 4. EXHAUST AND MAKE UP AIR MUST BE INTERLOCKED 5. PROVIDE AIR BALANCE REPORT 6. INCLUDE CAPTURE AND CONTAINMENT TEST |
|
| 08/19/2008 | MECHANICAL - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE LADDER TO ACCESS ROOF |