Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2005 | FRAMING | Approved | IVRS - Inspection :* | |
| 12/08/2005 | FRAMING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) DWV AND WATER OK |
|
| 12/02/2005 | FRAMING | Denied | IVRS - Inspection : Work is not complete enough to inspect.| 950* 1) 16" OF COPPER REQUIRED TO PEX AT WATER HEATER 2) SEAL VAPER BARRIER PENETRATIONS 3) NAIL PROTECT WIRES 4) WHIM 5050 HEADER AT 16" ON CENTER 3030 ALSO AND 5040 (ALL) 5) NAIL SHEAR 2 X 12 AT 8" ON CENTER 6) ANCHOR BOLTS LOOSE 7) LAV DIRTY ARM MUST BE 1 1/2" AND 42" TO VENT 8) NO GAS TEST 9) COMPLETE LATH 10) STOPPED INSPECTION |