Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2006 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 04/05/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OK TO COVER BATHROOM WALLS. 2. OK TO COVER VERTICAL PART OF ROOF DRAINS STILL NO REVISED APPROVED PLAN FOR ROOF DRAINS. |
|
| 03/28/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1. ROOF DRAINS INSTALLED WITHOUT BENEFIT OF A PLAN. PROVIDE APPROVED REVISION AND INSTALL CORRECTLY. REMEMBER PIPING IS TO BE SUPPORTED AT EACH CHANGE OF DIRECTION OR ELEVATION AND AT THE END OF BRANCHES, ETC. VERTICAL PIPING TO BE SUPPORTED NEED TO SEE CLOSET FLANGE 2. REREAD PLUMBING NOTE NUMBER 17 |
|
| 01/25/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. SUPPORT OVERHEAD PIPING PER PLAN GENERAL NOTE #4 P-1 EACH CHANGE OF DIRECTION OR ELEVATION AND THE END OF BRANCHES. 2. OK TO INSULATE HOT PIPING 3. NEED TO SEE CLOSET FLANGE |