| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/07/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) NO REVISED PLANS ON SITE 2) NO REDLINES AVAILABLE 3) CONTRACTOR HAS MODIFIED EXISTING PLUMBING SYSTEM TO PARTIALLY GAIN COMPLIANCE WITH 94 UPC IE... ADDING VENTS TO UNVENTER FLOOR SINKS AND BY ADDING PLUMBING FIXTURES TO ORIGINAL PLAN 4) AT GREASE TRAP: EXPOSE INLET CONNECTIONS FOR INSPECTION CONTRACTOR TO SUPPLY EXTENSION TO GRADE BY FINAL 5) PLUMBER TO ACCURATELY RED LINE, EXISTING (NEW) CONDITIONS BEFORE COVERING 6) OK TO COVER UNDERGROUND |
|
| 09/02/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) ABS IN EXPOSED EXTERIOR LOCATION 2) COPPER EXPOSED ON WALL NOT SUPPORTED, PROTECTED OR INSULATED 3) CHICAGO LOOP NOT APPROVED 4) VENT FOR FLOOR SINK IN BAR 5) VENT FOR FLOOR SINK IN KITCHEN 6) HAND SINK IN KITCHEN DRAIN/VENT 7) 3 COMP SINK-FLOOR SINK FOR 3 COMP 8) ADA ANZI 9) THIS INSPECTION IS FOR ROUGH SOIL ONLY |
|
| 08/23/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 07/29/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) REFER TO A-1 PLUMBING PLAN 2) NOT INSTALLED PER PLAN 3) ALL DIRECT WASTE PIPING TO BE PER 94 UPC |