Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T05CM02154

Parcel: 11202034A


Addresses:

3838 N CAMPBELL AV


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T05CM02154

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
11/14/2006 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
02/15/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*EAST SIDE STEM COLUMNS ??/
02/02/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*NORTH END EQUIPMENT PAD 2ND FLOOR, SOUTH END COLUMN FOOTING
12/30/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GRID LINE DD
12/28/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*EQUIPMENT PAD ON ROOF OK INFILL 2ND FLOOR OK
12/21/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRIDLINE 3- ??
12/12/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/09/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STAIRWAY FOOTING GRID 11-12 A-AA
11/29/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRID 11 THRU 13
AA THRU E OK
11/16/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRIDLINE 7-10 A-E
11/15/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*FOOTING ELEVATOR @ SOUTH END OK
11/10/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
11/08/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRIDLINE AA 6 FOOTING
11/07/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) LINE 1-4 GRID A TO E OK
11/02/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*ELEVATOR PIT FLOR # 3 GRID A-AA 1 THRU 10
10/31/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/19/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRIDLINE 1-C
10/18/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*GRIDLINE B-8 GRIDLINE E-1C