Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2005 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 09/29/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PARTIAL FOOTERS AND PERIMETER |
|
| 09/26/2005 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) INSTALL GRADE PINS OR NAILS TO VERIFY DEPTH OF CONCRETE FOOTING 2) INSTALL ALL BRASS SCREW UFER CLAMPS 3) SET PROPERTY PINS, INSTALL STRING LINES TO CHECK SETBACKS 4) MAINTAIN MINIMUM 3" CLEARANCE REBAR TO DIRT 5) STOPPED INSPECTION |