Permit: T05CM01916

Parcel: 141180790

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
07/08/2005 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
07/07/2005 EXCAVATION/LAYOUT REBAR & ZON Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) HAVE ALL ELECTRIC ADDED TO PLAN/PERMIT
2) EXPOSE VERTICALLY FTGS. TO VERIFY DEPTH
3) HAVE COPY OF PLANS EXISTING HOUSE BOLTS FROM HOUSE CONTRACTOR
4) NEED LADDER TO INSPECT ROOF
5) STOPPED INSPECTION
06/28/2005 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) VERIFY POST FTGS/ AND J-BOLT FOR POST ANCHOR AND STEEL (REBAR)
2) WHAT TYPE OF BOLT WAS USED FOR LEDGER, DID YOU DRILL INTO A BOND BEAM, HT ? OF BOND BEAM?
3) YOU HAVE A 3 GANG METAL ELECTRICAL BOX WITH WIRE COMING OUT OF THAT BOX, WHAT ARE THEY FOR AND WHERE DO THEY COME FROM HOW MANY CIRCUITS ARE YOU INSTALLING ? I SEE TWO FANS ONLY ON PLANS
4) NON-METALLIC CONDUIT TO BE 18" BELOW GRADE
5) GO AHEAD AND INSTALL ROOF DECK
6) NICE WORK BEAMS AND POSTS