Permit: T05CM01648

Parcel: 10120040D

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
03/01/2007 ENGINEERING - FINAL Approved FINAL GRADING APPROVED 2/28/07
10/27/2006 ENGINEERING - FINAL Denied The following items must be complete prior to final C of O.
1) Provide engineering cert. that basins and drainage ways have been constructed per the approved plans.
2) Clean all storm M.H.
3) Grout all storm M.H. frame and grate in place.
4) Complete sidewalk to ROW at SE corner of lot as shown on the approved grading plan.
5) Basin #1 is not constructed per plan, construct per plan or submit revision to city of review and approval.
6) Basin 3A not constructed. Construct per plan or submit revision to city of review and approval.
7) Storm M.H. in drive isle between basin 2 and 3B not found.
8) Repair erosion at concrete inlet to basin 2
9) Sidewalk not constructed between building and private drive as shown on approved grading plan.
06/01/2006 ENGINEERING - FINAL Partial Approval PARTIAL APPROVAL FOR ENGINEERING.
OK FOR TEMP C OF O ONLY.
PERMANENT C OF O NOT TO BE GIVEN UNTIL SITE WORK IN THE RIGHT OF WAY IS COMPLETE AND THE FINAL GRADING FOR PERMIT # T05BU01319 IS COMPLETED AND APPROVED.