Inspection History Details
Inspection Status: Approved
Inspection History: LANDSCAPE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/12/2006 | LANDSCAPE - FINAL | Approved | ||
| 05/11/2006 | LANDSCAPE - FINAL | Partial Approval | Ok for Temp. C of O. For Approval: DG for all disturbed areas including Pad area to the N.E. |
|
| 01/30/2006 | LANDSCAPE - FINAL | Partial Approval | OK for stocking only For approval complete site work, and landscape per plan. For Temp C of O: 1) Minimize construction activity (entire site) 2) Complete west ingress-egress along Kolb Rd. 3) Complete parking area striping (entire site) 4) Remove construction debris and dumpsters from parking area. 5) Rope off remaining construction areas not part of Lowe's site (including incomplete landscape) |
|
| 01/30/2006 | LANDSCAPE - FINAL | Partial Approval | OKAY TEMP C / O | |
| 01/06/2006 | LANDSCAPE - FINAL | Partial Approval | Ok for stocking only |