Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2007 | SITE - SEWER | Approved | ||
| 11/30/2005 | SITE - SEWER | Partial Approval | IVRS - Inspection :*M.H BASES HAVE BEEN POURED. OK TO STACK | |
| 11/28/2005 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :*NOT READY FOR INSPECTION SHALL SEE THE M.H BASE AFTER IT HAS BEEN POURED |
|
| 11/23/2005 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) FLEXIABLE COUPLINGS AT MAN HOLES ARE OK 2) CONNECTION TO M.H. #2 IS OK 3) OK TO BACKFILL TRENCH |
|
| 11/22/2005 | SITE - SEWER | Partial Approval | IVRS - Inspection :*SOIL WATER TEST IS OK 6" SITE SEWER FROM 5' OF BLDG TO M.H # 5 IS OK 6" SITE SEWER FROM M.H # 5 DOWNSTREAM TO M.H 4" WITHIN 5' OF M.H # 4 IS OK OK TO BACKFILL TRENCH NOTE: SHALL SEE M.H BASES PRIOR TO STACKING AND CONNECTION TO M.H #4 |