Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/27/2006 | ENGINEERING - FINAL | Approved | ||
| 10/26/2005 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED FOR "B" SECTION (EAST PORTION OF BLDG.) ."A" SECTION TEMP C OF O WAS APPROVED 9/16/05. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR T03BU03222 IS COMPLETED AND APPROVED. |
|
| 09/16/2005 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. 1. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR T03BU03222 IS COMPLETED AND APPROVED. 2. BARRICADE AREA AT THE SOUTHWEST CORNER OF THE BUILDING UNTIL THE SLOPE CONSTRUCTION IS COMPLETE AND SAFE. |
|
| 09/15/2005 | ENGINEERING - FINAL | Denied | 1. FINISH GRADING AROUND BUILDING 2. PROVIDE A 6' SIDEWALK ON THE EAST SIDE OF BLDG. 3. CONSTRUCT THE TRASH ENCLOSURE TO C.O.T. DEVELOPMENT STANDARD SPECIFICATIONS. |
|
| 09/09/2005 | ENGINEERING - FINAL | Denied | MET WITH MIKE BARTLETT/PATHWAYS DEV. AND JEFFERSON STEIN/ENGINEER. NEED REVISED AND C.O.T. APPROVED GRADING PLAN FOR INSPECTION PURPOSES. |
|
| 09/07/2005 | ENGINEERING - FINAL | Denied | 1. COMPLETE ALL SITE WORK 2. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. |