Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2005 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* | |
| 06/15/2005 | BUILDING PRE-SLAB | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NO H20 TEST 2) MAINTAIN MINIMUM 1/8" PER FT SLOPE 4" SEWER LINE 3) UNCOVER ALL PIPING 4) INSTALL 2 WAY CLEANOUT OUTSIDE ADDITION 5) MUCK OUT FOOTING (LOOSE DIRT) 6) REPLACE REBAR |
|
| 06/01/2005 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* 1) WILL NEED WATER TEST ON NEW SEWER LINE 2) UNCOVER CONNCTION NEXT TO BUILDING. 3) INSTALL 2 WAY CLEANOUT ( @ CLAY ABS CONNECTION) | |
| 05/27/2005 | BUILDING PRE-SLAB | Denied | IVRS - Inspection : See detailed listing on site.| 999* |